P. E. C. v Lesquende Ltd. [2003] JLR 485 (19 September 2003)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The word 'scheme' in the context of the Pointe Gourde principle is not limited in meaning and can encompass a range of activities, including re-zoning, provided there is sufficient factual linkage to the particular scheme.

Court disposition

judgment on interpretation of compensation principles

02

Material facts

Parties

P. E. C.

Applicant

Lesquende Ltd.

Respondent

03

Procedural history

  1. Posture

    Compulsory Purchase Compensation / Judgment

04

Questions and positions

Legal issues

Interpretation of the word 'scheme' under the Pointe Gourde principle in compulsory purchase compensation

Party arguments

Applicant
The word 'scheme' should be narrowly construed and not include past, present, or future activities such as re-zoning.
Respondent
The word 'scheme' is wide enough to include past, present, and future activities, including re-zoning, if sufficiently linked to the particular scheme on the facts.

05

Court’s reasoning

  1. 01

    Pointe Gourde principle

    The word 'scheme' under the Pointe Gourde principle does not have a special meaning and is wide enough to include past, present, and future activities, including re-zoning, if sufficiently linked to the particular scheme on the facts.

06

Ratio, limits and disposition

Ratio decidendi

The word 'scheme' in the context of the Pointe Gourde principle is not limited in meaning and can encompass a range of activities, including re-zoning, provided there is sufficient factual linkage to the particular scheme.

Court disposition

judgment on interpretation of compensation principles

Source and reliance status

Official court record

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Court record

Judgment

[2003] JLR 485

[ Home ] [ Databases ] [ World Law ] [ Multidatabase Search ] [ Help ] [ Feedback ] [

DONATE ] Jersey Law Reports You are here:

BAILII >> Databases >> Jersey Law Reports >> P. E. C. v Lesquende Ltd. [2003] JLR 485 (19 September 2003) URL: https://www.bailii.org/je/cases/JLR/2003/JLR030485.html Cite as: [2003] JLR 485 [ New search ] [ Help ] P. E. C. v Lesquende Ltd. 2003 JLR 485 (19 September 2003) Planning Law-compulsory purchase-principles of compensation-Pointe Gourde principle-word "scheme" does not have special meaning under Pointe Gourde principle-wide enough to include past, present and future activities, including re-zoning, if sufficiently linked to particular scheme on facts The document you wish to view is available to registered users or can be purchased as a PDF. To purchase this document in PDF format or alternatively to Register to purchase membership go to the Jersey Law website via this link: 2003 JLR 485 BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII URL: https://www.bailii.org/je/cases/JLR/2003/JLR030485.html

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Pointe Gourde principle

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.