The application failed because the plaintiff did not provide a satisfactory explanation for the nearly three-year delay after dismissal and over two years after the Chief Justice’s practice directions, despite procedural irregularities in the dismissal process. The court held that the plaintiff was guilty of laches, did not meet the threshold for equitable relief, and that the overriding objective could not be used to excuse inordinate unexplained delay.
Source excerpt
- Reinstatement of suit
- Dismissal for want of prosecution
- Notice to show cause
- Delay and laches
- Overriding objective