22 Feb 2019
BUDA PIPE REHAB ENG CO LTD v. CPC CONSTRUCTION HONG KONG LTD
- Citation
- [2019] HKCFI 503
- Court
- Court of First Instance
- Case number
- HCCT69/2018
The Schedule did not apply to the BP Contract because there was no written arbitration agreement between LW and CPC as required by section 101; alternatively, even if the Schedule applied BP failed to identify the question(s) of law or show the arbitrator was 'obviously wrong' on matters that were primarily findings of fact (waiver/estoppel and interim quantum); accordingly leave to appeal and other relief were refused and the originating summons dismissed with indemnity costs.