2 Jun 1999
Terraform Engineering Co. Ltd. v. Full Wealth Investment Ltd.
- Citation
- Terraform Engineering Co. Ltd. v. Full Wealth Investment Ltd.
- Court
- Court of Appeal
- Case number
- CACV251/1998
The Court dismissed the appellant's appeal holding the arbitrator erred in law by purporting to grant an extension of time which the contract did not authorize; the claimant had abandoned its breach claim at arbitration and could not resurrect it on appeal; the Supplemental Agreement fixed completion at 16 January 1996 and imposed liquidated damages, so the arbitrator's award could not stand; accordingly the Court upheld the lower court's setting aside of the award and dismissed the appeal with costs ordered to the respondent.