15 Apr 1994
THE ATTORNEY GENERAL v. SHIMIZU CORPORATION
- Citation
- THE ATTORNEY GENERAL v. SHIMIZU CORPORATION
- Court
- Court of First Instance
- Case number
- HCMP3071/1993
The court held the declarations sought were in substance advisory and did not concern rights of the plaintiff that were determinative; the construction dispute as to the main contract was for the arbitrator and the originating summons was therefore inappropriate and amounted to an abuse/meritless proceeding, warranting striking out and an order for costs in favour of the defendant.