10 Mar 2022
HIP HING CONSTRUCTION CO LTD v. HONG KONG AIRLINES LTD
- Citation
- [2022] HKCFI 622
- Court
- Court of First Instance
- Case number
- HCCT72/2021
Defendant has established an arguable set‑off/counterclaim limited to the basement leakage which raises triable issues of attribution and quantum; however, Defendant failed to particularise or credibly evidence the large sums claimed (HK$212m remedial and HK$40m pa training) except for a credible QS estimate of remedial works of HK$21m. Accordingly, summary judgment is entered for the Plaintiff for the outstanding sum save for allowance of HK$21,000,000 to reflect the arguable set‑off; the Defendant bears the burden at trial to establish its counterclaim and set‑off and the court directs furt…