15 Jun 2000
TRIDANT ENGINEERING CO. LTD. v. MANSION HOLDINGS LTD.
- Citation
- TRIDANT ENGINEERING CO. LTD. v. MANSION HOLDINGS LTD.
- Court
- Court of First Instance
- Case number
- HCCT3/1996
Clause 25 of the KGJV/Tridant main contract was incorporated into the Tridant/Mansion sub-contracts; Mansion materially breached express and/or implied obligations to proceed regularly and diligently, failed to provide adequate materials, plant, labour and supervision and wrongfully refused to order major plant/materials unless Tridant substituted Mansion Fire, conduct which objectively amounted to repudiation; Tridant validly accepted repudiation and lawfully terminated the FS and PD sub-contracts and recovered damages of HK$15,798,893 plus an indemnity for further claims; Mansion Fire succe…