24 Dec 1998
TRIFAIRCO ENGINEERING CO. LTD. v. WISHING STAR LTD.
- Citation
- TRIFAIRCO ENGINEERING CO. LTD. v. WISHING STAR LTD.
- Court
- Court of First Instance
- Case number
- HCA9563/1996
The court found no binding promise by the Plaintiff to deliver by end of January 1996, held the parties proceeded on the delivery schedule in the second programme, concluded the Plaintiff did not cause actionable delay and the Defendant failed to prove defects causally attributable to the Plaintiff; accordingly judgment on liability is for the Plaintiff and the counterclaim is dismissed.