31 May 2019
JOIN EASE INVESTMENT LTD v. DIRECTOR OF LANDS
- Citation
- [2019] HKLdT 38
- Court
- Lands Tribunal
- Case number
- LDLR11/2016
The Tribunal refused extension of time and leave to appeal because the delay (36 days past deadline) was substantial and inexcusable, the applicants therefore had to show a real prospect of success and they failed to do so; materially, under section 12(c) LRO the tribunal correctly excluded any building or development potential based on prospective Small House Policy/ding rights because no building licences or enforceable rights existed as at the resumption date; substitution of the executrix was permitted for two matters to validate proceedings; costs were awarded to the respondent.