21 Mar 2007
SAM WOO BORE PILE FOUNDATION LTD v. CHINA OVERSEAS FOUNDATION ENGINEERING LTD
- Citation
- SAM WOO BORE PILE FOUNDATION LTD v. CHINA OVERSEAS FOUNDATION ENGINEERING LTD
- Court
- Court of Appeal
- Case number
- CACV113/2006
The strikeout order was interlocutory and therefore did not give the plaintiff an as‑of‑right appeal to the Court of Final Appeal under s22(1)(a); the issues raised were not of great general or public importance; on the proper construction of the specific subcontract and factual matrix the phrase "1.5m in depth (min)" placed the risk of additional toeing‑in depth on the subcontractor and the interplay between Bills of Quantities and the SMM/Particular Preamble depends on the particular contract terms.