10 Jun 1983
MITSUI CONSTRUCTION CO LTD v. ATTORNEY GENERAL
- Citation
- MITSUI CONSTRUCTION CO LTD v. ATTORNEY GENERAL
- Court
- Court of First Instance
- Case number
- HCCL1/1983
Clause 13 makes the billed quantities the measure of the work included in the Contract Sum so that substantial automatic increases in executed quantities may constitute Additional Works/variations; such variations fall within Clause 74(4) permitting re‑rating (notwithstanding an extension of time under Clause 65(4), which is subject to other contract provisions); contractor is entitled to re‑rating and compensation under Clause 74(4) for losses causally linked to using excess quantities to cope with ground conditions; Site Instructions were not variation orders because the delegated authority…