15 Jun 2001
CHUNG FAI ENGINEERING CO. (a firm) v. MAXWELL ENGINEERING CO. LTD.
- Citation
- CHUNG FAI ENGINEERING CO. (a firm) v. MAXWELL ENGINEERING CO. LTD.
- Court
- Court of Appeal
- Case number
- CACV981/2000
The appeal is dismissed because the judge's factual findings were not shown to be wrong, the 12 August target in the supplemental agreement was not of the essence and was not pleaded as such, and Maxwell's inability to complete by that date was excused by impediments beyond its control (lack of power and water).