5 Dec 2005
WIDE PROJECT CONSTRUCTION (HK) LTD v. THE NCORPORATED OWNERS OF YEN DACK BUILDING
- Citation
- WIDE PROJECT CONSTRUCTION (HK) LTD v. THE NCORPORATED OWNERS OF YEN DACK BUILDING
- Court
- Court of First Instance
- Case number
- HCA3759/2002
The court has jurisdiction to open and review interim certificates; on the evidence (including contemporaneous documentation and expert assessments) the defendant failed to prove widespread non-completion or defect except in limited respects (defective work at 4 opened-up locations, failure to remove screws/nails externally, and failure to procure the surety bond). Accordingly the 5th and 6th certificates are to be adjusted (Concrete Repair Works 95% complete with 5% outstanding; roof plant room waterproofing 100%; roof waterproofing assessed at 80%), the defendant's purported termination of…