IAN RICHARD CARVER CULLEN, T/A IAN CULLEN & ASSOCIATES v. KAISILK DEVELOPMENT LTD
- Citation
- [2019] HKCFI 2206
- Court
- Court of First Instance
- Case number
- HCA584/2017
The court construed the 1st Agreement to mean that where the provider's works ceased before completion of the compensation process paragraph 4.3 entitled the provider to charge on a time basis and paragraph 4.5 made such charges payable within 14 days of issue of the debit note; applying that construction, the plaintiff's time‑basis claim under the 1st Agreement was time‑barred. The court found the 2nd Agreement (contingency bonus) and the 3rd Agreement (lump sum for Rule 20) were valid and supported by consideration and were not time‑barred; the defendant did not establish an unequivocal ant…