22 Dec 2016
HO LOY AND ANOTHER v. DIRECTOR OF ENVIRONMENTAL PROTECTION
- Citation
- HO LOY AND ANOTHER v. DIRECTOR OF ENVIRONMENTAL PROTECTION
- Court
- Court of First Instance
- Case number
- HCAL21/2015
The Director lawfully approved the EIA Report and granted the permit because the Report satisfied the Study Brief and Technical Memorandum requirements: CAD validly confirmed operational inputs, PRD airspace assumptions were not a required precondition for EIA input assumptions (flight tracks and utilisation were properly stated), on‑site mitigation measures and proposed operational compensation were adequate and feasible, cumulative impacts were properly addressed within the Study Brief scope, and no additional common law consultation or inquiry duties arose beyond the statutory EIA process;…