Hong Kong Case Law: Decisions & Judgments | LexChat

Hong Kong Case Law

As-built drawings
  • 4 Mar 2011

    LIANG JIAN XING v. JINGO INTERIORS DESIGN LTD

    Citation
    LIANG JIAN XING v. JINGO INTERIORS DESIGN LTD
    Court
    District Court
    Case number
    DCCJ5986/2008

    The completion date was validly varied by mutual agreement to 11 November 2008 (evidenced by construction programs, communications and a meeting), so no liquidated damages were payable; the defendant was liable for specified defective works and the court quantified reasonable rectification costs (HK$42,550) but the defendant was entitled to contractual payments (including HK$13,500 under the Design Agreement and various VO sums), yielding a net judgment for the defendant of HK$52,851.82; costs awarded by departure from usual rule (order nisi for 75% in favour of defendant).