4 Mar 2002
YING HO COMPANY and Others vs THE SECRETARY FOR JUSTICE
- Citation
- YING HO COMPANY and Others vs THE SECRETARY FOR JUSTICE
- Court
- Court of First Instance
- Case number
- HCA10834/1998
Only a narrow implied term was necessary: if culpable/unreasonable government delay prevents the grantee complying with building covenant periods, the period must be extended for that delay. Court found no culpable delay by Government between May 1994 and April 1996, no binding agreement by SPEL to grant free extensions, and the premia paid were valid consideration for forbearance. Therefore plaintiffs' principal claims fail and payments under protest are not recoverable absent duress or bad faith, neither of which was made out.