13 Jul 2006
GLOBAL BRIGHT ENGINEERING LTD v. CWF PILING & CIVIL ENGINEERING CO LTD
- Citation
- GLOBAL BRIGHT ENGINEERING LTD v. CWF PILING & CIVIL ENGINEERING CO LTD
- Court
- Court of First Instance
- Case number
- HCMP1242/2006
Leave to appeal was refused because the Court was satisfied the trial judge’s factual finding that the defendant was responsible for 14 days delay was justified on the evidence (discovery of defects timeline), so the consequent awards for liquidated damages and delay costs could not be upset; the $13,000 discrepancy was insufficient to justify an appeal given costs.