19 Dec 2017
FORCE WAY ENGINEERING LTD v. THE INCORPORATED OWNERS OF GRAND COURT
- Citation
- FORCE WAY ENGINEERING LTD v. THE INCORPORATED OWNERS OF GRAND COURT
- Court
- District Court
- Case number
- DCCJ3216/2016
The fourth stage payment certificate was validly issued under the contract but not final, binding and conclusive; the IO was entitled to litigate defects and set off its losses against the certified sum; the certificate of practical completion was invalid because the IO did not participate in the required joint inspection and therefore practical completion did not occur; the IO lawfully accepted the Contractor's repudiatory breach and terminated; the IO was entitled to recover reasonable rectification costs and liquidated damages which were applied against certified sums and retention money,…