4 Feb 2005
CHU CHEE HA t/a SHOWREEL FILM FACILITIES v. AUDIO CONSULTANTS CO LTD
- Citation
- CHU CHEE HA t/a SHOWREEL FILM FACILITIES v. AUDIO CONSULTANTS CO LTD
- Court
- District Court
- Case number
- DCCJ4074/2003
Court found the operative contract arose when plaintiff paid on 10 December 1997; there was no proved agreement on a specific delivery date and extrinsic evidence was admissible to show the written quotations did not represent the full agreement; plaintiff failed to prove an agreed deadline or that defendant repudiated or that plaintiff accepted any repudiation; defendant entitled to counterclaim damages totaling HKD 59,670 plus interest and costs.