29 Nov 2002
JIMHO INTERNATIONAL LTD. v. FLOWER-POWER GMBH
- Citation
- JIMHO INTERNATIONAL LTD. v. FLOWER-POWER GMBH
- Court
- District Court
- Case number
- DCCJ3221/1999
Defendant failed to prove on the balance of probabilities the existence of the alleged oral agreements and the asserted water damage; disputed documents were unreliable and explanations inconsistent; accordingly set-off was not established and plaintiff is entitled to judgment for the unpaid invoice with interest and costs.