7 Jan 2016
KIM HUNG CONSTRUCTION & ENGINEERING CO LTD v. STANDARD REFRIGERATION & ENGINEERING CO LTD
- Citation
- KIM HUNG CONSTRUCTION & ENGINEERING CO LTD v. STANDARD REFRIGERATION & ENGINEERING CO LTD
- Court
- Court of Appeal
- Case number
- CACV90/2015
The tentative possession dates in SP 6.02 and related documents were provisional and not contractual dates; the arbitrator erred in law by treating them as contractual and by relying on pleaded/factual admissions as admissions of contractual breach, and accordingly the interim award on the delay claim was set aside and the appeal dismissed.