25 Sept 1985
PERFECT MARBLE COMPANY LIMITED v. TAO YUN COMPANY LIMITED
- Citation
- PERFECT MARBLE COMPANY LIMITED v. TAO YUN COMPANY LIMITED
- Court
- Court of First Instance
- Case number
- HCA6851/1984
Defendant failed to discharge the onus of proving an agreed completion date and liquidated damages; silence and non‑return of a duplicate letter did not establish acceptance; parts of the delay were not the plaintiff's fault; therefore plaintiff entitled to the unpaid contract balance plus interest and costs.