3 Sept 2002
Re Po Wing (International) Construction Ltd.
- Citation
- Re Po Wing (International) Construction Ltd.
- Court
- Court of First Instance
- Case number
- HCMP6668/2001
The CRC acted within the lawful discretion reserved by the General Guidelines and the Building Authority to determine the necessity and scope of interviews; given the applicant's limited and outdated foundation experience, conducting a full interview and recommending a three-month deferral was not capricious or unreasonable, so the applications for relief were refused.