21 Dec 2005
GRANDEUR ELECTRICAL CO LTD v. CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD
- Citation
- GRANDEUR ELECTRICAL CO LTD v. CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD
- Court
- District Court
- Case number
- DCCJ6782/2004
Clause NS11 confers only an option to arbitrate exercisable by serving a Notice to Refer to Arbitration within 28 days of the Contract Manager's decision or inability to decide; no such notice was served here, therefore there was no arbitration agreement and the consent stay was not permanent—the interim stay is liftable.