31 May 2010
MR. TONG PUN CHUNG v. BLESSGAIN CONSTRUCTION ENGINEERING LTD
- Citation
- MR. TONG PUN CHUNG v. BLESSGAIN CONSTRUCTION ENGINEERING LTD
- Court
- District Court
- Case number
- DCCJ4618/2008
The Court found the oral agreement incorporated payment by reference to CLP final measurement and verification at rates 18% less than the Schedule of Rates, the eight certificates were interim/provisional not final, a final accounting was required, the Court accepted the Defendant's calculated total work of HK$1,279,371.30, allowed a net set of contra-charges after disallowing specific unproven deductions, and held the Defendant must pay the Plaintiff HK$63,225.25 with interest from 4 September 2008 and costs on an order nisi basis.