8 Jul 2016
FORTUNE LINK ENGINEERING CO LTD v. SUI CHONG CONSTRUCTION & ENGINEERING CO LTD
- Citation
- FORTUNE LINK ENGINEERING CO LTD v. SUI CHONG CONSTRUCTION & ENGINEERING CO LTD
- Court
- District Court
- Case number
- DCCJ2929/2012
Leave to amend was granted; pre-judgment interest awarded from 28 December 2009 (invoice date plus 14 days) at HSBC best lending rate plus 1% per annum; the Defendant's summons for partial costs or issue-based apportionment dismissed and costs follow the event; the Plaintiff's non-compliant sanctioned-letter of 12 February 2014 was treated as a Calderbank offer and, because the Defendant unreasonably rejected it, indemnity costs were ordered to run from the date of rejection (17 February 2014); the Defendant must pay party-and-party costs before 17 February 2014 and indemnity costs thereafter…