10 Aug 2000
AQUALITY ENGINEERING CO. LTD. v. WELL TECH GEOWORKS ENGINEERING LTD.
- Citation
- AQUALITY ENGINEERING CO. LTD. v. WELL TECH GEOWORKS ENGINEERING LTD.
- Court
- Court of First Instance
- Case number
- HCA12756/1999
The Court found the April 29, 1999 meeting and the signed Schedule of Works constituted conclusive evidence of the agreed value of work (HK$7,282,267), the Defendant failed to establish a bona fide defence or an arguable issue under Order 14 (no binding back-to-back terms or notorious trade custom), and the Defendant's contra charges were wholly unsubstantiated; accordingly summary judgment was granted for the Plaintiff for the claimed sum with interest and costs.