6 Jun 2001
OTIS ELEVATOR CO (HK) LTD v. CHUN WO BUILDING CONSTRUCTION LTD
- Citation
- OTIS ELEVATOR CO (HK) LTD v. CHUN WO BUILDING CONSTRUCTION LTD
- Court
- Court of First Instance
- Case number
- HCCT9/2001
Because there was no unequivocal admission of liability and quantum and the arbitration clause was not challenged as invalid or inoperative, the court had no discretion but to grant a mandatory stay in favour of arbitration and dismiss the plaintiff's summary judgment application.