12 Sept 2008
RE PINE GROWTH MANUFACTURING CO LTD
- Citation
- RE PINE GROWTH MANUFACTURING CO LTD
- Court
- Court of First Instance
- Case number
- HCCW322/2006
The court construed the order as requiring the parties to cooperate and act reasonably in appointing a valuer; the correct course is to offer Grant Thornton appointment on the identical capped terms tendered by Baker Tilley and, if Grant Thornton refuses, to appoint Baker Tilley; inspection must proceed with provision of soft-copy documents on DVD at a reasonable charge and the parties must jointly approach the bank to establish requirements for releasing the petitioner from guarantees.