6 Dec 2012
NEWELL CURTAIN WALL & ENGINEERING CO LTD v. SUNYARDS ENGINEERING LTD
- Citation
- NEWELL CURTAIN WALL & ENGINEERING CO LTD v. SUNYARDS ENGINEERING LTD
- Court
- Court of First Instance
- Case number
- HCCT55/2010
Clause 6 of the Letter of Acceptance constituted a condition precedent: the subcontract did not become effective until mock-up approval by the Architect and Po Lin Monastery. No such approval was given because the mock-ups and required tests did not comply with contractual and Building Department requirements; the defendant was principally at fault for failing to prepare adequate fabrication shop drawings, to undertake required testing and to maintain quality control. Consequently the subcontract never took effect and the plaintiff is entitled to restitution of advance payments. Judgment ente…