TUNG PO DECORATION ENGINEERING LTD v. GREAT BRIGHT ENGINEERING LTD
- Citation
- [2024] HKDC 1086
- Court
- District Court
- Case number
- DCCJ4853/2020
Plaintiff failed to prove substantial performance or that the 3rd PAF Work Record was verified by the Defendant; the Court gave no weight to either party's 3rd PAFs absent evidence of site inspection and rejected the Plaintiff's unsupported >99% (or >90%) completion assertions; omission to call Mr Lam permitted adverse inference; the Plaintiff repudiated the contract when its director left the site on 4 January 2020 and effectively abandoned works; compute contractual entitlement upon completion at HK$946,000 less agreed deductions and payments to HK$374,884.10; allow Defendant repudiatory da…