13 Nov 2024
SKYFORCE ENGINEERING LTD v. WANG KWONG ELECTRICAL ENGINEERING LTD
- Citation
- [2024] HKDC 1860
- Court
- District Court
- Case number
- DCCJ273/2021
The defendant's continuous suspension of works from 28 September to 17 October 2019 constituted a repudiatory breach; plaintiff was entitled to accept that repudiation on 17 October 2019 and to engage replacement works and recover damages; plaintiff's withholding under clause 18 and limited payment delays were not repudiatory; certain variation claims by defendant lacked contemporaneous proof and were reduced or rejected; net judgment reflects set-off of allowed counterclaim.