4 May 2004
DECOR FLOORS ENGINEERING LTD v. YUEN HUNG WAI
- Citation
- DECOR FLOORS ENGINEERING LTD v. YUEN HUNG WAI
- Court
- District Court
- Case number
- DCCJ1637/2003
Delivery period commenced upon deposit confirmation (the bank confirmation received 24 September 2002); therefore delivery in early November 2002 was within the 6–8 week contractual period; the defendant accepted the measured area (597.64 sq.m.) and no joint re-measurement was required, entitling the plaintiff to the outstanding balance of $144,172 plus interest and costs; defendant's counterclaim for delay is dismissed.