29 Jul 2025
WING LOK CONSTRUCTION & ENGINEERING CO LTD v. TECHOY CONSTRUCTION CO LTD
- Citation
- [2025] HKCFI 3310
- Court
- Court of First Instance
- Case number
- HCCT2/2023
Leave to amend was refused because the proposed amendments were late, inadequately particularised, and in part bound to fail or be useless on the Plaintiff's own evidence; permitting them would cause real prejudice and disruption to the PTR and trial timetable. Only a single consequential amendment to paragraph 5A of the Reply and Defence to Counterclaim was allowed; all other amendment applications were dismissed and costs awarded to the Defendant with a Certificate for Counsel.