13 Apr 2012
UNISON PROJECTS CO LTD v. AHL DESIGN WORKSHOP LTD
- Citation
- UNISON PROJECTS CO LTD v. AHL DESIGN WORKSHOP LTD
- Court
- Court of First Instance
- Case number
- HCCT37/2010
Court held that a binding subcontract existed on the terms of the 5 November 2009 quotation and drawings; AHL breached payment terms and Unison was entitled to suspend on 26 April 2010 but Unison remained offsite for an unreasonable period without electing to affirm or terminate, which permitted AHL to engage others and treat Unison's conduct as repudiatory; consequent net accounting produced judgment for Unison in the sum of HK$3,636,246 after allowing and disallowing specified claims and set‑offs, with interest and an employee's compensation indemnity in favour of Unison.