8 Jan 2015
RE NGLE PUSHAN POWER LTD
- Citation
- RE NGLE PUSHAN POWER LTD
- Court
- Court of First Instance
- Case number
- HCMP2780/2014
The court granted extensions where the statutory criteria were met and where there remained potential prosecution risk; where breaches were older than three years applications were withdrawn; materially, acts of attempting to present accounts after the statutory deadline do not change the date of default and therefore do not create a fresh risk of prosecution so NGLE did not require relief for the periods 24 March 2009 to 31 December 2011.