31 May 2016
ERIC CHAN & CO.v. WONG KWOK WANG WARREN
- Citation
- ERIC CHAN & CO.v. WONG KWOK WANG WARREN
- Court
- District Court
- Case number
- DCCJ1155/2008
Final judgment for HK$508,221 was entered (16 March 2016). Pre‑judgment interest awarded to the plaintiff from the date of issue of the writ (17 March 2008) to 25 April 2013 at the conventional rate of prime plus 1% per annum; the court disallowed pre‑judgment interest for the period from and including 26 April 2013 to 16 March 2016 because the plaintiff unreasonably pursued an unwarranted appeal which caused delay. Post‑judgment interest runs from the date of Final Judgment until satisfaction. The Mareva injunction was not wrongly made; the defendant's application for damages under the under…