1 Dec 1999
RE PO SUN CONSTRUCTION & ENGINEERING LTD.
- Citation
- RE PO SUN CONSTRUCTION & ENGINEERING LTD.
- Court
- Court of First Instance
- Case number
- HCCW246/1999
The petition was dismissed because the Company raised bona fide disputed set-offs (including delay, occupation and indemnity issues) which meant the alleged debts were not established for winding-up purposes, and there were no opposing/supporting creditors or public interest to justify continuation of the petition.