19 Jan 2005
YUEN CHONG FIRE ENGINEERING CO LTD v. NGO KEE CONSTRUCTION CO LTD
- Citation
- YUEN CHONG FIRE ENGINEERING CO LTD v. NGO KEE CONSTRUCTION CO LTD
- Court
- District Court
- Case number
- DCCJ3761/2004
The court found that practical completion of the Sub-Contract works occurred on 19 July 2003, that the subsequent works instructed on 25 July 2003 were therefore a separate contract, and that Clause 22 applies only to disputes arising out of the Sub-Contract; accordingly the arbitration clause did not cover the Plaintiff's claim and the Defendant's application to stay and refer to arbitration was dismissed.