19 Jul 2013
ALLCOM LTD v. LEUNG CHUN BONG
- Citation
- ALLCOM LTD v. LEUNG CHUN BONG
- Court
- Court of First Instance
- Case number
- HCA1749/2010
The DLO letter of 21 January 2010 did not constitute a letter of waiver or tolerance nor did it state the DLO would not take immediate action; it expressly reserved Government rights. The supplemental agreement unambiguously required production of such a letter on or before 7 June 2010. The plaintiff failed to produce the required letter and therefore breached the supplemental agreement, entitling the defendant to forfeit HK$1,450,000; plaintiff's claim is dismissed with costs to defendant.