Sign in
India Source-linked decisions Coverage checked

India Case Law

Search judgments by proposition, citation, court, judge or legal topic, then move directly into the source-grounded case analysis.

Courts on this page
0 court collections
Last checked

India decisions

Decisions matching the current search

Clear filters
Constitutional law

Karnataka Power Transmission Corporation Limited v. Rekha & Ors.

The Supreme Court held that writ petitions for electrocution compensation are not maintainable where disputed facts exist, and compensation must be assessed on a just, fair basis.

  • Maintainability of writ petition under article 226
  • Electrocution compensation
  • Strict liability
  • Absolute liability
  • Compensation methodology
  • Disputed questions of fact
Read case analysis
Electricity law

INDIAN RAILWAYS versus WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED & ORS.

The Supreme Court held that Indian Railways does not qualify as a deemed distribution licensee under the Electricity Act because its electric traction and distribution installations are confined to captive operational use and do not perform the statutory function of supplying electricity to consumers in an area of supply; accordingly Indian Railways is a consumer for electricity procured through open access and is liable to pay Cross-Subsidy Surcharge and Additional Surcharge; draft legislative proposals do not alter this statutory position.

  • Deemed distribution licensee
  • Cross-subsidy surcharge
  • Additional surcharge
  • Open access
  • Appropriate government
  • Section 11 railways act 1989
Read case analysis
Criminal law

MAHAVEER versus STATE OF MAHARASHTRA AND ANR

The prosecution failed to prove beyond reasonable doubt that any artificial means not authorised by the licensee were employed to abstract energy or that the meter had been injured or tampered with; therefore the presumption under Section 39 and the statutory circumstances under Section 44 were not attracted, the High Court's reversal of the trial court's acquittal was unsustainable on the facts, and the appellant must be acquitted.

  • Theft of energy
  • Interference with meters or licensee's works
  • Improper use of energy
  • Presumption
  • Use of artificial means
  • Holes in the meter box
Read case analysis
Electricity law

HARYANA POWER PURCHASE CENTRE (HPPC) AND OTHERS versus GMR KAMALANGA ENERGY LIMITED AND OTHERS

The Supreme Court upheld the concurrent findings of the CERC and the APTEL that coal allocations (firm and tapering linkage) were made for the project as a whole and any shortfall met through imported/open market coal must be apportioned pro rata among all beneficiaries/DISCOMs in proportion to energy supplied; no substantial question of law arose under Section 125 CPC s.100 to warrant interference and GRIDCO was not a necessary party to the Section 63 petitions, therefore both appeals were dismissed.

  • Change in law
  • Force majeure
  • Allocation of coal linkage
  • Second appeal under section 125
  • Substantial question of law
  • Impleading parties
Read case analysis
Electricity law

M/S KKK HYDRO POWER LIMITED versus HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED AND OTHERS

Section 86(1)(b) of the Electricity Act, 2003 mandates that fixation of price for purchase of electricity and PPAs incorporating such price must be subject to review and approval by the State Commission; since the supplementary PPA dated 10.09.2010 effecting enhancement from ₹2.50 to ₹2.95 per kWh was not placed before or approved by the Commission, it could not be enforced. However, the Court declined to disturb the APTEL order awarding a weighted average tariff (and the Commission's consequential order) because HPSEB had not appealed and the revised tariff had been acted upon for a long tim…

  • Section 86(1)(b) electricity act, 2003
  • Power purchase agreement
  • Tariff determination
  • State commission approval
  • Small hydel power projects
  • Regulations 2007
Read case analysis
Electricity law

CHAMUNDESHWARI ELECTRICITY SUPPLY COMPANY LTD. (CESC) versus SAISUDHIR ENERGY (CHITRADURGA) PVT. LTD. & ANR.

Because the Developer did not obtain an extension under Article 5.7 nor issue the notice required by Article 14.5, the preconditions for invocation of Article 4.4 were satisfied and CESC validly encashed the performance security; the State Commission and APTEL erred in treating the delay as Force Majeure and directing restoration, extension and renegotiation contrary to the express contractual scheme.

  • Performance bank guarantee
  • Force majeure
  • Power purchase agreement
  • Conditions precedent
  • Contractual timelines
  • Tariff renegotiation
Read case analysis
Electricity law

NABHA POWER LIMITED versus PUNJAB STATE POWER CORPORATION LIMITED AND OTHERS

Press Release dated 01.10.2009 is not 'law' under Article 13 and only subsequently published notifications (e.g. 11.12.2009 and 14.12.2009) could amount to law; appellants failed to satisfy essential FTP prerequisites (goods must be movable and 'manufactured in India', supply must be by main/sub-contractor, and procurement must follow ICB where required), therefore they were not entitled to deemed export benefits under Para 8.3 of the FTP and are not entitled to restitutionary compensation under the PPA.

  • Deemed export benefits
  • Foreign trade policy 2009-2014
  • Change in law (ppa article 13)
  • Power purchase agreement
  • Restitutionary relief/compensation
  • International competitive bidding
Read case analysis
Electricity law

BSES RAJDHANI POWER LTD. & ANR versus UNION OF INDIA AND ORS

Tariff must be cost-reflective; a regulatory asset is an exceptional, regulatory measure recognizing an uncovered revenue gap and must be limited in quantum and time: guided by Rule 23 a regulatory asset should not exceed a reasonable percentage (Rule 23 prescribes 3% of ARR as guiding principle), any newly created gap must be liquidated within three years, and the existing regulatory asset shall be liquidated within a finite period (the Court directed liquidation of the existing regulatory asset in a maximum of four years starting 01.04.2024), Regulatory Commissions must provide a roadmap an…

  • Regulatory asset
  • Tariff determination
  • Regulatory failure and regulatory capture
  • Aptel powers under section 121
  • Accountability of regulatory commissions
  • Rules/regulations governing liquidation of revenue gap
Read case analysis
Electricity law

GUJARAT URJA VIKAS NIGAM LIMITED versus GREEN INFRA CORPORATE WIND PRIVATE LIMITED AND OTHERS ETC.

GUVNL could not, by virtue of PPAs containing a tariff applicable only to projects availing accelerated depreciation, bind respondent projects that did not in fact avail accelerated depreciation to that tariff in perpetuity where GUVNL had not secured written commitments from them to avail accelerated depreciation; the GERC and APTEL were correct in holding the respondents entitled to approach the GERC for project-wise tariff determination, and the appeals were dismissed.

  • Determination of tariff
  • Power purchase agreements
  • Accelerated depreciation
  • State instrumentality obligations
  • Renewable energy policy
Read case analysis
Electricity law

THE STATE OF HIMACHAL PRADESH & ANR. versus JSW HYDRO ENERGY LIMITED & ORS.

CERC Regulations, 2019 (including Note 3 of Regulation 55) limit the proportion of free energy for home State (FEHS) that may be taken into account for tariff determination to 13% but do not prohibit a generating company from supplying free power beyond 13% under a contractual Implementation Agreement; accordingly the Implementation Agreement was not overridden by the Regulations and the High Court erred in modifying the Agreement by writ when the regulatory forum and appellate mechanisms under the Electricity Act were available and the CERC's order addressed only PPAs/PSAs and was not appeal…

  • Free power to home state (fehs)
  • Cerc regulations, 2019
  • Note 3 of regulation 55
  • Implementation agreement
  • Writ jurisdiction of high court
  • Tariff determination
Read case analysis

About this LexChat collection

India decisions are organised by court, judge, legal area and indexed issue so a practitioner can move from a proposition to a citable authority with the surrounding context intact.