The CLU dated 13.12.2021 was unlawful because the site was zoned rural agricultural under the operative Master Plan and the PRTPD Act prescribes that any alteration of land use must follow the statutory procedure (ss.70,75,76); the Planning Board's approval on 05.01.2022 could not retrospectively cure the jurisdictional defect or operate as an amendment of the Master Plan without compliance with the statutory revision process; siting norms and prior environmental clearance requirements were not satisfied; consequently the CLU and related pollution consent (insofar as based on it) were quashed…