Viscount v Treanor
Viscount v Treanor [1969] JJ 1243 (01 December 1969)
The court held that, under Jersey common law, a stipulated sum for delay in completion may be reduced if excessive; the English penalty/liquidated damages distinction does not apply.
- Damages for delay
- Liquidated damages
- Penalty clauses
- Construction-law
- Contract-law
- Damages-for-delay