19 Feb 2025
J&T EXPRESS (MALAYSIA) SDN. BHD. 1. ) AER EMPIRE SDN BHD 2. ) MUHAMMAD MURSHID BIN ABU HASSAN
- Citation
- BA-22NCC-157-08/2024 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCC-157-08/2024 (Mahkamah Tinggi)
Court held there was no evidential basis that the plaintiff agreed to reduce the outstanding debt; minutes of the 30 May 2024 meeting did not show any consent to a reduction, no evidence supported the alleged RM160,000 renovation payment or overcharge for July rentals, and the documentary record supported the plaintiff’s calculation. Therefore no triable issue existed and summary judgment was entered for the plaintiff for RM1,005,682.67; costs RM20,000 awarded to plaintiff.