PEMPETISYEN MUDAJAYA CORPORATION BERHAD THB POWER SDN BHD
- Citation
- WA-28NCC-187-02/2025 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-28NCC-187-02/2025 (Mahkamah Tinggi)
The court held that the adjudication decision created an enforceable entitlement and the respondent failed to establish a bona fide dispute on substantial grounds or to show immediate means of payment; without prejudice communications relied upon in the parties' affidavits were properly before the court or waived; therefore enforcement by winding up was appropriate and the winding-up petition is allowed, while the competing motion to appoint private liquidators is dismissed on the facts.