8 Nov 2022
SUCCESS INPUT SDN BHD PRISTAR HOUSING DEVELOPMENT SDN. BHD.
- Citation
- AA-A52NCvC-153-09/2019 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- AA-A52NCvC-153-09/2019 (Mahkamah Sesyen)
Plaintiff failed to prove that rectification works were completed to the satisfaction of the Architect/Engineer; therefore under Clause 7.4 the Defendant was justified in withholding the retention sums under Clause 10.2. Separately, on the Sewerage Contract the Court found Plaintiff had fulfilled its contractual obligations and Defendant's counterclaim lacked independent evidence from IWK, hence the counterclaim failed.