14 Feb 2025
NZ BINA SDN BHD 1. ) REAPLITE INDUSTRY SDN BHD 2. ) OCBC BANK (MALAYSIA) BERHAD PIHAK TERKILAN Kerajaan Malaysia
- Citation
- JA-22NCvC-275-12/2017 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- JA-22NCvC-275-12/2017 (Mahkamah Tinggi)
Court found Plaintiff's termination of the sub‑contract unlawful because cogent evidence showed delays were caused by lack of possession, unfinished utility works and JKR payment delays, not the 1st Defendant; progress claims Nos.35‑37 were submitted and acknowledged by Plaintiff; therefore Plaintiff's claim for LAD was dismissed and 1st Defendant entitled to return of performance bond and unpaid progress claims.