7 Jul 2025
ICON CITY DEVELOPMENT SDN BHD LEE KEAN HWA dan 61 yang lain
- Citation
- 02(i)-3-01/2025(W) (Mahkamah Persekutuan)
- Court
- i
- Case number
- 02(i)-3-01/2025(W) (Mahkamah Persekutuan)
The Federal Court held that the 42-month delivery period runs from the date of the Period of Approval, which for these SPAs is the date of the first/original approval of the Building Plans obtained within the Approval Period, not from the expiry of the Approval/Extended Approval Period nor from the date of the last amended building plan approval; the issue was a pure question of law suitable for summary judgment; any ambiguity is resolved contra proferentem against the developer; appeal dismissed and summary judgment and costs affirmed.