10 Nov 2023
AWP PROPERTIES SDN. BHD. CARLSON CONSTRUCTION SDN. BHD.
- Citation
- WA-24C-65-04/2023 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-24C-65-04/2023 (Mahkamah Tinggi)
The AD was partly set aside because the adjudicator exceeded his jurisdiction by determining the termination to be unlawful and defective when the contract was pleaded as mutually terminated and the issue of validity of termination was not contested, thereby depriving AWP of its set‑off; conversely the court found no breach of natural justice regarding the 'time at large' finding and declined to disturb that factual/legal conclusion.